DCMA Check #5: Hard ConstraintsThis check calculates percent of incomplete tasks with hard constraints. Hard Constraint types include:
Hard constraints prevent tasks from being moved with predecessor duration, start and finish times change. FormulaTargetPercent of Finish-to-Start (FS) predecessor relationships should be greater than 90% CommentsUsing list of task issues (the list at the top of Diagnostics dialog box) you can find tasks with hard constraints. See also |