Forum: Project Portfolio Risk Management
Topic: Importing Risks from Excel
Replies: 4
Views: 10082

Re: Importing Risks from Excel

Here is another important note. Some our clients ask us if Excel spreadsheet needs to be formatted any specific way to be imported to RiskyProject. The only requirement is Risk Register spreadsheet will need to have each risk as a row and risk properties, including risk names, probability and impact...
by Intaver Support
Mon Sep 13, 2021 8:27 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Compatibility and sharing files between versions causing issues
Replies: 1
Views: 110

Re: Compatibility and sharing files between versions causing issues

RiskyProject versions are always backwards compatible, but they are not forwards compatible. In practical terms what does this mean. You can open files from older versions, in newer versions (backwards compatibility); however, because the new versions are not just an update, but are new software wit...
by Intaver Support
Mon Sep 13, 2021 8:27 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: actual costs
Replies: 1
Views: 108

Re: actual costs

If you are not using resources as part of your cost calculations then it is straight forward. As activities are completed, you can update cost either in your management schedule or in RiskyProject in the Income and Cost view. On the other hand, if you are using a resource loaded schedule to calculat...
by Intaver Support
Mon Aug 02, 2021 12:48 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Pert Analysis Toolbar
Replies: 1
Views: 502

Re: Pert Analysis Toolbar

Microsoft Project implements one the Quantitative Risk Analysis technique PERT (Program Evaluation and Review Technique). The PERT model was developed in 1950s to address uncertainty in the estimation of project parameters. According to classic PERT, expected task duration is calculated as the weigh...
by Intaver Support
Mon Aug 02, 2021 12:46 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Scatter Plot Percentile Setting
Replies: 1
Views: 508

Re: Scatter Plot Percentile Setting

The Cost vs Duration Scatter Plot uses a slider to set the P-value for schedule (Cost or Finish Times) and the resulting chance of meeting Cost and Schedule at the selected percentile.

Image
by Intaver Support
Mon Aug 02, 2021 12:40 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Weekly Exception Calendars
Replies: 1
Views: 533

Re: Weekly Exception Calendars

We don't have working weeks exceptions in our calendars in RiskyProject. This would significantly slow Monte Carlo simulations. So all working weeks are the same. We can do exceptions based on individual days and day of week. It is probably possible to use individual day exception and replicate it f...
by Intaver Support
Sat Jun 26, 2021 11:44 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Percent % Complete vs % Work Complete
Replies: 1
Views: 793

Re: Percent % Complete vs % Work Complete

While % Work Complete is useful for managing project progress, it is not recommended for schedule risk analysis as this setting will add additional complications to the creation of a valid risk model. The main objective of schedule risk analysis is to forecast probabilities for finish times and dura...
by Intaver Support
Sat Jun 26, 2021 11:43 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Recommended Practices for integrating resources and schedule risk analysis
Replies: 1
Views: 784

Re: Recommended Practices for integrating resources and schedule risk analysis

While resource loaded schedules and schedule risk analysis are not incompatible, how you approach a risk analysis depends upon your objectives as resource loading can introduce additional complications. Depending upon your objectives this could mean creating a specific schedule for your risk analysi...
by Intaver Support
Sat Jun 26, 2021 11:42 am
Forum: Project Portfolio Risk Management
Topic: Linking Google Docs to Risks
Replies: 1
Views: 929

Re: Linking Google Docs to Risks

In RiskyProject Enterprise you can attach or link documents to specific risks in the Risk Information > Documents tab. Documents that can be linked to a risk include Google docs. There are 2 methods that you can use to link your Google docs to a risk: directly link to an online document or, creating...
by Intaver Support
Sun Jun 06, 2021 12:51 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Accessing raw cost simulation data
Replies: 1
Views: 827

Re: Accessing raw cost simulation data

I am assuming you are referring to the Meters on the Project Summary (or Project Information in the Addin). The calculation used is can be seen by clicking the ? on the bottom right corner of the meters. https://www.intaver.com/images/RP_Forum_ScoreMeter.png The raw cost data can be copied from the ...
by Intaver Support
Sun Jun 06, 2021 12:45 pm
Forum: Project Portfolio Risk Management
Topic: Schedule Reports that show Uncertainty Bands.
Replies: 1
Views: 748

Re: Schedule Reports that show Uncertainty Bands.

Short answer is no. I was thinking that they could be flagged in a text column and filtered but our Text columns do not support filtering. Workaround might be to use a Text Column to flag activities that use Risk Bands > Export the Schedule the Excel and apply the filter to the target column (Risk B...
by Intaver Support
Sun Jun 06, 2021 12:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Importing Costs from Excel
Replies: 1
Views: 992

Re: Importing Costs from Excel

Currently, we don't this capability implemented directly. We do integrate with Excel, but where you can import data is limited to: - import risk register with their properties - import probabilities and impact of risks. Excel import is expandable in that we can link to additional fields, we would re...
by Intaver Support
Tue May 04, 2021 9:24 pm
Forum: Project Portfolio Risk Management
Topic: Analyzing mega schedules
Replies: 2
Views: 12849

Re: Analyzing mega schedules

In depends on schedule, particularly on number of repeated activities. We tried this algorithm on very many real life schedules. If schedule is relatively small, for example, less than 1000-1500 activities, in our experience reduction will be 5-10%. Some large schedule contain many repeated activiti...
by Intaver Support
Tue May 04, 2021 9:16 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Calculating the Cost of Residual Risk
Replies: 3
Views: 2909

Re: Calculating the Cost of Residual Risk

If you have assigned a cost to a mitigation plan and assigned it to a risk this is used only for the post-mitigation calculation and does not affect the simulation results. For example, we create a response plan in the Mitigation/Response view with a Cost of $25000. http://www.intaver.com/images/RP_...
by Intaver Support
Tue May 04, 2021 9:10 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Configuring Risk Matrix for Quantitative Risk Analysis
Replies: 1
Views: 1074

Re: Configuring Risk Matrix for Quantitative Risk Analysis

The reason for this for qualitative risk analysis standard 5 x 5 risk matrix works well as you are only "placing" the risk onto the matrix using a simple probability x impact with subjective scores (1,2,3,4,5) or labels (very low, low,.. etc), From this you get a simple score e.g 3*5= 15 and the ris...