1. Is it necessary to populate the Risk Register before doing a quantitative analysis?
2.How do I view/print histograms of the quantitative analysis results? (I\'m using RiskyProject Lite)
Do I need to populate the register?
Moderator: Intaver Support
Do I need to populate the register?
Project manager
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Re: Do I need to populate the register?
Simple answer is no. If you are doing a straight forward SRA using Base, Low and High estimates, you do not need to involve anything from the Risk Register.
The Lite version only provides a very simplified high level reports on the risk analysis (see the 3*3 Report). To generate histograms, cum probability, and tornado reports, you will need to try the Professional version.
Intaver Support
The Lite version only provides a very simplified high level reports on the risk analysis (see the 3*3 Report). To generate histograms, cum probability, and tornado reports, you will need to try the Professional version.
Intaver Support
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Re: Do I need to populate the register?
Where default risk probability and outcome is comming from? I would like to set default probability equal 20% not 15%.
Project manager
-
- Posts: 1018
- Joined: Wed Nov 09, 2005 9:55 am
Re: Do I need to populate the register?
Default probability and outcome is defined in Schedule -> Options -> Risk.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com