Decision Analysis for Projects

You have project schedule, which is created in RiskyProject or imported from other project management software. This project schedule has a number of alternative scenarios. So, RiskyProject converts the project schedule into a decision tree. Each activity within the project schedule becomes a node of the decision tree. If an activity has more than one successor, you can define it as a decision node, end node, or event chance node of the decision tree. If the activity is defined as a decision node, this means that, by the end of this activity, a decision will be made on what course of action will be taken. For event nodes, you can define probabilities associated with each branch.