Comparing pre and post-mitigation baselines

  1. Open the Risk Register view (Risk tab of the workflow bar).
  2. Click the Configure Pre and Post Mitigation button.
  3. Select baselines for Pre and Post Mitigation.


Risk mitigation

See also

Analyzing Risk Mitigation Efforts with Multiple Baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans
Assigning a mitigation or risk response plan to a task