User's Guide to  

RiskyProject

Back to RiskyProject
Project Risk Management and Decision Analysis 

Site search powered by Google

Adding a predecessor to a task


1. Select the task to which you want to add a predecessor.
2. Open the Task Information dialog box.
3. Click the Predecessor tab.
4. On the first row of the grid, click in the Task Name cell. A drop-down list appears containing a list of all available tasks or type
5. Select the predecessor from the drop-down list. By default, the predecessor type is Finish- Start (FS).
6. If required, enter a lag time
7. Click OK.


You cannot make a task be a predecessor to itself
You cannot create a schedule that it will lead to a circular relationship between tasks
You cannot link a summary task to one of its subtasks
You cannot link two tasks twice.


See also

Setting up your projects

www.intaver.com products      solutions      support      partners      technology      company

Copyright Intaver Institute Inc., 2002-2009. All Rights Reserved