Enabling and disabling risks


You can enable or disable each risk assignment. If risk assignment is disabled it does not affect project schedule and calculation to risk impacts. However, it stays in the risk register and remains assigned to the tasks or resources.
1. Open a risk assignment view:
      Global Risk Assignment view
      Local risk assignment views for tasks and resources
      Risk tabs in the Task Information and Resource Information dialog boxes.
2. Enable a risk by clicking on the check box beside the Risk name. Clear the check box to disable the risk.

 

See also

Risk Register

Assigning local and global risks