Managing Default Risk Categories


Risks are defined by categories.. These categories are used in the intial risk identification and later in risk assignments. The default risk categories for for non-schedule risks can be added or modified. 

1. On the Risk menu, click on Risk Outcomes.

2. Click the Outcomes tab.

3. Modify, add, or delete categories as required.

 

See also

Risk Register

Risks in RiskyProject