Setting Milestones


You can flag a task as a milestone. If you turn on a milestone, the task bar within a Gantt chart is displayed as:
Milestones

Any task with zero duration is automatically displayed as a milestone in the Gantt chart; however, any task can be marked as a milestone. The milestone flag is for display only and does not affect the project calculations.
If a task has no duration entered, it is automatically displayed as a milestone and you do not have to complete the following steps. If you want to flag a task that has duration, complete the following steps.

1. Select the task that you want to flag as a milestone.
2. Open the Task Information dialog box.
3. Click the Advanced tab.
4. Select the This task is a milestone check box.
5. Click OK.


See also

Predecessors and Lags

Constraints

www.intaver.com products      solutions      support      partners      technology      company

Copyright © Intaver Institute Inc., 2002-2009. All Rights Reserved