User's Guide to  

RiskyProject

Back to RiskyProject
Project Risk Management and Decision Analysis 

Site search powered by Google

Viewing Resource Allocation

 

The Resource chart shows the time allocation for a selected resource.

 


For the resource chart to open, two conditions must be met:
•  You must select the Chart check box for a resource in the resource sheet.
•  The selected resource must be assigned to a task.


You can select four different types of resource charts:
•  Peak units: The highest level at which a resource is scheduled for all assigned tasks during a given period.
•  Work: The total number of hours a resource is scheduled for all assigned tasks during a given period.
•  Overallocation: A resource is over allocated when it has more work assigned than can be done in the resource's available time. Overallocation is number of hours a resource is scheduled for all assigned tasks over resource's available time. Overallocation can be presented only for work (not material) resources.
•  Percent allocation: The percentage of a resource's capacity taken up by all of its assigned tasks during a given period. Percent allocation is only available for work (not material) resources.

 

Selecting the resource chart type


1. Select the Chart check box associated with the resource.
2. Right-click on the Resource chart and choose one of chart types from the shortcut menu.


Overallocation for work resources is calculated based on Maximum Units, defined for the resource in the Resource view. For example, if maximum units are 150%, overallocation can be work above 150%.

See also

Resource calendars

Managing Resources and Work

Managing Resources and Work

www.intaver.com products  

     solutions      support      partners      technology      company

Copyright © Intaver Institute Inc., 2002-2009. All Rights Reserved