Tracking Performance

 

Tracking is an important step in the project risk management workflow. You add tracking information in the Tracking tab of the Task Information dialog box. Tracking information is shown on the Result Gantt views.

Tracking information is not included in the current schedule (deterministic) calculation. The progress of summary tasks is a function of its subtasks; therefore, you cannot add tracking data to summary tasks. RiskyProject will calculate tracking data for summary task and complete project automatically.

 See also

Tracking Results

Viewing Tracking Data

Task Information Tracking