Assigning Low and High Estimates for Duration and Cost for Group of Tasks

 

You may assign statistical distribution for duration and fixed cost for a selected group of tasks:
1. Open the Gantt View.
2. Select a group of tasks.
3. Right-click on a Task ID.
4. Select Set Low/High Duration or Low/High Fixed Cost.
5. Enter fixed values and a coefficient to calculate Low and High duration or cost based on Base duration or Cost.
6. Click OK to apply changes.

Low and high durations and/or fixed cost will be automatically calculated. If you already manually entered low and high values for fixed cost and duration, the procedure will overwrite these values.

 

See also
Adding 3-point estimates

Assigning Low and High Estimates for Duration and Cost for Group of Tasks