Task Dependencies

The type of link between different tasks. There are four types of task dependencies:
•  Finish-To-Start: Task 2 (successor) cannot start until task 1 (predecessor) finishes
•  Start-To-Start: Task 2 (successor) cannot start until task 1 (predecessor) starts
•  Finish-To-Finish: Task 2 (successor) cannot finish until task 1 (predecessor) finishes
•  Start-To-Finish: Task 2 (successor) cannot finish until task 1 (predecessor) starts
Task dependencies can be defined in Task Information dialog box (predecessor tab). They also can be defined toolbar button within standard toolbar.

 