Risk Register
The
risk register is a set of all risk in the project. The risk register
can be populated in two ways:
1. Directly entering risk information into the risk register view.
2. Using the Global Risk Assignment view, Local risk assignment
views for tasks and resources, or risk tabs in Task Information
dialog and resource information dialog. Any new risks entered using
these views and tabs will be automatically added to the risk
register.
Risk registers include the following information:
• Risk names: Each risk name is unique. You
cannot define risk with the same name within risk register.
• Risk parameters: risks can
be opened and closed, risks or issues, assigned to different tasks
or resources, and risk properties (dates, owner, contact,
description, etc.).
• Calculated risk
parameters: probabilities, impact,
and scores, is this risk threat, opportunity or both.
Opening the Risk Information dialog box
Double-click on any risk ID to open the Risk information
dialog box. There you can enter risk parameters, assign risks to
tasks and resources, and view risk mitigation information.
|