Defining working time


RiskyProject allows you to define multiple calendars. All calculations are done internally in hours and minutes.
1. From the Tools menu, choose Working Time.
2. Select a calendar from the Calendar list. There are five calendars provided:
    • Standard
    • Morning Off
    • Afternoon Off
    • 24 hours
    • Night Shift
3. If you need to modify the selected calendar, click on a day in the calendar. The working and nonworking time is displayed in the schedule on the right. You may define working for specific weekday. To do it just click on weekday and modify working times for the weekday. You may also specify working time for the specific day. To do it just click on specific day and modify working times.
4. Click on an hourly period to set it as working or nonworking time. White is working, pink is nonworking.
5. Once you have completed the calendar, click OK to save the changes.

 

See also

Setting up your projects

Defining work for task types